Two drawings of the same bracket: one with everything at ±0.1, one with a single Ø12 H7 bore and an Ra 0.8 face. The geometry is identical and the material is identical, so they get the same price. The second one should cost about a fifth more, and the shop that quotes them the same finds out on the inspection bench.

Where the cost of a tolerance comes from

A tight tolerance is not expensive because of the number on the drawing. It is expensive because of four things it makes you do:

A worked example

An aluminium bracket, 50 off. Machine A$120 an hour with its operator, inspection labour A$65 an hour, A$7.50 of material per blank, 10% overhead and 25% margin on cost.

All ±0.1With H7 bore and Ra 0.8
Setup60 min80 min
Cycle per part6.0 min7.2 min
Inspection per part0.2 min (sampled)1.0 min (every part)
Good parts planned97% (52 blanks)93% (54 blanks)
Unit priceA$31.49A$38.42

The difference is A$6.93 a part, 22% of the price. Split by cause, per part including overhead and margin:

CauseAdds per part
Finishing pass (1.2 min more cycle)A$3.43
Scrap allowance (2 more blanks, run and inspected)A$1.20
Measuring every partA$1.19
Longer setup (20 min)A$1.10

None of these is large on its own, which is why they are easy to leave out. Together they are most of the margin on the part.

What to look for on the drawing

Ask before you price it

Many tight tolerances are copied from an old drawing or set by a default in the CAD template. A short question, "is H7 needed on the Ø12, or would ±0.05 do?", costs nothing, and buyers often agree. If they do not, you have a reason for the price that you can show them: the finishing pass, the gauge, the scrap.

Spindlewise reads PDF and scanned drawings attached to a quote and lists the fits, tolerances of ±0.02 or tighter, Ra 0.8 or finer finishes, threads and heat treatment it finds, next to the attachment, so they are in front of you while you build the routing. The extra operation, setup and inspection time and the yield go into the quote like any other line, and every price shows the cost behind it.